Where a major estate's pipeline is actually stuck
The question
Which planning applications in Westminster over the last three months relate to a major institutional landowner, and how are they progressing?
Data used
The finding
A raw search returned 65 matches. Reading every proposal description individually removed unrelated hits: buildings with similar names, incidental wording: leaving 39 genuinely relevant records. Grouped into seven themes and cross-tabulated against decision status, the outcome was 22 approved, 17 pending and 0 refused. Every one of the four major redevelopment schemes was still undecided, while routine items cleared quickly and almost always favourably.
Why it matters
Approval rates alone would suggest a frictionless authority. The theme split shows the opposite: consent risk is concentrated entirely in the large, value-driving schemes, and programme assumptions should be built around that asymmetry rather than the headline rate.
Caveat